A variance is a subtraction with a sign that means something. Cost variance and schedule variance are how you stop saying 'a bit behind' as if it were a measurement. Negative is unfavourable for both. The arithmetic is not the hard part. The hard part is not rounding the story back into a fog.
Cost variance: EV minus AC
Cost variance (CV) = EV − AC. Using the running figures: $40,000 − $50,000 = −$10,000. You have earned ten thousand less than you spent. That is over budget on the work done, not 'the budget is half gone so we are fine.' Half gone with 40% earned is the opposite of fine.
Positive CV means you delivered that work for less than its budgeted value. Enjoy it briefly, then ask why — cheaper vendor, skipped test, or a definition of done that quietly shrank. A pretty CV that was bought by undeclared scope cut is a fraud with a green cell.
CV is about the work completed, not the work remaining. A healthy CV on a thin slice of the project can still hide a disaster in the next package. Report it with the percentage complete so nobody thinks a small sample is the whole novel.
Schedule variance: EV minus PV
Schedule variance (SV) = EV − PV. Here: $40,000 − $50,000 = −$10,000. You have earned ten thousand less than the plan said you would have earned by this date. That is behind schedule in money units, which offends people who wanted days. It is still the standard measure because it uses the same currency as the baseline.
SV does not tell you whether the critical path is late. A team can earn value on fat, easy packages while the one task that gates go-live sits untouched. Use SV as a portfolio health number, then look at the network. Treating SV as a substitute for the critical path is how late projects have cheerful charts.
Positive SV means more budgeted work is done than was scheduled by now — ahead. Same scepticism applies: did you sequence the valuable work, or the work that was easy to tick? Earned value rewards completion. It does not automatically reward completion of the right thing.
Read CV and SV as a pair
Both negative: over budget and behind — our example. You are late and expensive on what you have finished. That is a delivery problem, not a reporting problem. Both positive: ahead and under — rare, and worth checking you have not forgotten a chunk of scope.
Negative CV, positive SV: you bought speed with money — overtime, extra vendors, crashing. That can be a conscious trade. Say so. Positive CV, negative SV: you are cheap and late, which often means the team is under-resourced or blocked, not 'efficient.' Cheap delay is still delay.
Zero is on plan, not a moral victory. And a variance without a date is a rumour. Always pair the numbers with the status date and the BAC so a sponsor can see the scale. −$10,000 on a $100,000 project is not the same conversation as −$10,000 on a $4 million programme. The formula does not know that. You do.
Summary & next steps
CV = EV − AC. SV = EV − PV. Negative is unfavourable. Our example is −$10,000 on both: overspent on the work done, and behind the plan. Read them together, then check the critical path before you celebrate or panic.
Next: performance indexes — the same figures as ratios, which is how you talk about efficiency instead of a one-off gap.