Earned value management is three numbers that must not be allowed to merge in a status sentence: what you planned to have earned by now, what you have actually earned, and what you spent getting it. Mix them and you will report 'we are at 60%' to a sponsor who thinks that means time, money, and product in the same breath. It does not.
Planned value: the authorised work you meant to have finished
Planned value (PV) is the budgeted value of the work scheduled to be completed by the status date. If the performance measurement baseline said four of ten equal packages should be done by now, and the budget at completion (BAC) is $100,000, PV is $40,000. PV is a statement about the plan, not about reality.
You cannot invent PV in the meeting. It comes from a baselined schedule with a budget spread across the work — often a time-phased cost baseline. If you have no baseline, you do not have earned value. You have a conversation and a spreadsheet that agrees with whoever last edited it.
PV moves only when the baseline moves through change control, or when the calendar reaches the next planned chunk of work. It does not move because the team feels busy. Feelings do not have a BAC.
Earned value and actual cost: progress versus the receipt
Earned value (EV) is the budgeted value of the work actually completed. If those ten packages are $10,000 each and three are done to the agreed definition of done, EV is $30,000 — even if you are in week four, even if people worked weekends. EV is about product, measured in the same money units as the baseline. It is not hours. It is not optimism.
Actual cost (AC) is what you spent to achieve that EV. Labour, vendors, licences — the real outflow. If you have spent $35,000 to complete those three packages, AC is $35,000. AC does not care what you planned to spend. Receipts are stubborn like that.
The usual smear is reporting '% complete' without saying of what. Percent of calendar, percent of budget spent, and percent of scope done are three different stories. EV forces you to pick the third and price it at budgeted rates. That is the whole trick. It is not mysticism. It is refusing to let spend impersonate progress.
A small walkthrough you can reuse
Take a project with BAC = $100,000, ten equal work packages, ten weeks. At the end of week five the plan said five packages done, so PV = $50,000. The team has finished four packages to the definition of done, so EV = $40,000. Finance shows $50,000 spent, so AC = $50,000.
In English: you are halfway through the calendar and halfway through the budget, but only 40% of the authorised work is done. You have spent the money of five packages to buy four. Anyone who reports 'we are at 50%' without those three letters is choosing a comforting denominator.
Hold these three figures still. The next lessons will subtract and divide them. If you cannot explain PV, EV, and AC on a whiteboard with round numbers, do not proceed to indexes. An index built on a muddled EV is a confident error.
Summary & next steps
PV is the budgeted value of work scheduled by now. EV is the budgeted value of work actually finished. AC is what you spent. Same units, three meanings. Our running example: PV $50,000, EV $40,000, AC $50,000, BAC $100,000.
Next: cost and schedule variance — subtraction that tells you whether the gap is money, time, or both.